Field test Romania
Field test activities:
- Advancement of monitoring solutions for distribution grids
- Installation of mobile phasor measurement units (PMUs) as configurable monitoring nodes
- Tracking and evaluation of energy distribution and voltage quality
- Six months monitoring campaign with data fusion within FISMEP
Objectives:
- Demonstrating the FISMEP platform's ability to integrate information on energy distribution and voltage quality
- Implementation of an electric energy market that can operate at different voltage levels (transmission vs. distribution)
Project partners involved:
Test sites:
- LV grid node on UPC campus, Bucharest
- LV grid node with PV installation
- 20/0.4 kV substation (on LV side)
- Point of common coupling (PCC) of wind park, 20 kV and 110 kV
Read detailed description